ANNUAL WATER MAIN REPLACEMENT PROJECT
For the month of October, 2021 the contractor will begin installation of new water main on 9th Court between Marguerita Ave and Carlyle Ave, 23rd Court between California Pl N and Washington Pl S., and on Adelaide Place between 7th St and dead end. The contractor will also continue testing and connecting the newly installed water main on 6th St between Ocean Park Blvd and Pier Ave and Raymond Ave between 4th Street and 6th Street and installation of meter boxes on 18th Court between Delaware Ave and Pico Blvd; Traffic on 18th Court, 6th Street, Raymond Ave, and 2nd Street will be closed to through traffic. Please use alternate routes whenever possible. If you have any questions or concerns, please contact Carlos Rosales at carlos.rosales@smgov.net or (310) 458-2201, x2620.

ADVANCED TRAFFIC MANAGEMENT SYSTEM, PHASE 5 PROJECT
For the month of October, 2021, this project will upgrade the traffic signal equipment at four locations and install fiber optic cables along Montana Ave and 26th St.; The project will provide transit priority along the corridor, allow for real-time remote monitoring and management of the traffic signals, provide public Wi-Fi along the corridor, and connect the San Vicente Reservoir and the Montana Avenue Branch Library to the City’s network. We appreciate your patience during the project, to provide this safety improvement and public enhancements. If you have any questions or concerns, please contact Jay Dinkins at jay.dinkins@smgov.net or (310) 458-8291.

CITY YARDS MODERNIZATION PROJECT
For the month of October, 2021, construction will impact the project area located at 2500 Michigan Ave, which will affect the sidewalk and parking lane on the north side of Delaware Ave just east of 24th St. Please contact Senior Construction Manager Sebastian Felbeck at sebastian.felbeck@smgov.net or (310) 434-2675 with any questions/concerns regarding this project.

ALLEY RENEWAL PROGRAM
For the month of October, 2021, thru December 2021, Street Maintenance Crews will begin alley repair work as part of the Alley Renewal Program in the 200 Blk of 16th Court. The scope of this work involves alley resurfacing and water box upgrade. This project is citywide and will involve repairs across multiple locations from 8am to 3:300pm. Please use alternate routes whenever possible. If you have any questions or concerns, please contact Tyler Brown at tyler.brown@smgov.net or (310) 458-8212.

NON-POTABLE WATER MAIN PROJECT
For the month of October, 2021 the contractor will be performing restoration and striping on Ocean Ave, Olympic Drive and Main Street. The contractor will maintain one lane of traffic in each direction on Ocean Avenue, Olympic Drive and Main Street. Please use alternate routes whenever possible. If you have any questions or concerns, please contact Carlos Rosales at carlos.rosales@smgov.net or (310) 458-2201, x2620.

ANNUAL PAVING AND SIDEWALK REPAIR PROJECT
For the month of October, between Monday, October 18 through November 12, 2021, City of Santa Monica contractor Excel Paving will grind out top 2-inch layer of the asphalt street and repave with new fresh asphalt pavement. Heavy equipment will be necessary to construct the new roadway. Due to reduced traffic lanes, please expect delays. One-lane traffic in each direction will be maintained. Street parking will not be available. This work will take approximately 4-5 weeks.
Street pavement resurfacing segments are:

Olympic Water Transmission Main and Well Equipping Project
For the month of October 2021, the contractor will begin digging to identify existing utilities on Texas Avenue between Saltair Ave and Centinela Ave, Arizona Ave between Centinela Ave and Berkeley St, and on Berkeley St between Arizona and Olympic Blvd. If you have any questions or concerns, please contact Carlos Rosales at carlos.rosales@smgov.net or (310) 458-2201, x2620.

Safe Streets for 17th Street and Michigan Ave Project
For the month of October, starting on October 11, crews will be starting work on 17th Street between Olympic Boulevard and Michigan Ave for the first stages of work:

Comments