Know Before You Go
Wastewater Main Replacement Project
For the week of May 8, the Contractor will continue will continue with rehabilitation of existing maintenance holes throughout the City. During
Week of May 1, 2017
Wastewater Main Replacement Project
For the week of May 1, the Contractor will continue with rehabilitation of existing maintenance holes throughout the City. During these
Know Before You Go
Ishihara Park (Buffer Park) Project
As part of the construction of the new Buffer Park at 2909 Exposition Blvd, ‘NO PARKING’ signs will be posted along
Know Before You Go
Ishihara Park (Buffer Park) Project
As part of the construction of the new Buffer Park at 2909 Exposition Blvd, ‘NO PARKING’ signs will be posted along
Ishihara Park (Buffer Park) Project
As part of the construction of the new Buffer Park at 2909 Exposition Blvd, ‘NO PARKING’ signs will be posted along portions of Exposition Blvd
Ishihara Park (Buffer Park) Project
As part of the construction of the new Buffer Park at 2909 Exposition Blvd, ‘NO PARKING’ signs will be posted along portions of Exposition Blvd
Week of January 9, 2017
Current Projects:
1. Wastewater Main Replacement Project
2. Ishihara Park Project
3. Los Amigos Park Stormwater Harvesting and Direct Use Demonstration Project
4. Berkeley Street
Know Before You Go
Week of December 5, 2016
Wastewater Main Replacement Project
For the week of Dec. 5, the contractor will begin restoration and final paving of the trench
Wastewater Main Replacement Project
For the week of Nov. 28, the contractor will continue with replacement of the sewer main on Alta Pl. N. between 4th Street and 7th Street.
Know Before You Go
For the Week of Oct. 17
Wastewater Main Replacement Project
For the week of Oct. 17, the contractor will continue restoration work on manholes at the
Wastewater Main Replacement Project
For the week of October 3, the contractor will continue restoration work on manholes at the following locations (California Avenue at 1st Court, Virginia Avenue at
Wastewater Main Replacement Project
For the week of Sept. 19, the contractor will begin restoration work (concrete restoration of alley approach, pavement of trench) on Palisades P. N. between 4th