> ## Content Index
> Fetch the complete content index at: https://www.smdp.com/llms.txt
> Use this file to discover other available public pages before exploring further.

# Letter: Temporary Civic Center sports field
- URL: https://www.smdp.com/temporary-civic-center-sports-field/
- Published: 2016-05-25T13:00:43.000Z
- Updated: 2024-12-03T21:46:15.000Z
- Author: Guest Author
- Tags: Letters, Opinion, California, california coastal commission, city manager, city of santa monica, civic center, coastal area, Los Angeles, News, parking, rick cole, Santa Monica, santa monica california, santa monica civic center, santa monica news, santa monica parking, SMMUSD, sports, sports field, #wp, #wp-post, #Import 2025-11-06 14:39

Editor:

Recognizing that field space for our community is imperative, as City Manager, I’m recommending immediate funding to design a "temporary" multi-use sports field in the Civic Center with synthetic turf, fencing, lighting and portable restrooms. It is premature to program construction funding for three reasons: (1) the design process will give us a much more accurate estimate of the project’s actual construction cost (currently reflected as $3.25m in FY18-19); (2) we will be working with our partners at the Santa Monica Malibu Unified School District on opportunities for joint use and perhaps some form of joint funding; and (3) we will need to work with the Coastal Commission and the County Courts on strategies for addressing the loss of parking in the Civic Center and coastal area.

I have heard from a number of community members that the time line to start construction of the field is too far out. Constructing a field is many facets. We have put together the following rough and very accelerated planning and construction schedule, recognizing the potential for unanticipated delays:

Council approval of Capital Improvement Budget - June 2016

RFP for design, evaluate proposals, Council approval, and contract execution - October 2016

Design development, community outreach, and Coastal Commission approval (contingent upon parking relocation) - May 2017

Construction documentation - July 2017

Plan check - January 2018

Issue bids for construction, evaluation, Council award, contract execution - June 2018

Construction start - July 2018